We can no longer keep up
B-What day is today?-
It’s been a long time since we’ve been in touch, and not because nothing has happened or because we’re not interested in keeping you up to date. We simply don’t have enough time to write down all the events that are happening here. We often think that we should take more photos and enjoy the whole thing more, but then the next call comes in, usually with an assignment.
But we don’t want to complain. We love what we do and every day we look at the new building with awe and sometimes can hardly believe what is being created – and at what speed. We celebrated the topping-out ceremony on Friday and finally the weather can no longer get in our way. How often have our lovely craftsmen stood in the pouring rain on the construction site in recent weeks?
The first bookings for the new rooms are trickling in via the website and on the phone and we are so grateful that there are so many curious people who, like us, are eagerly awaiting the opening. This will take place in mid-October. So if you still need a bit of wellness for the colder days in fall, book your room directly with us.
Now some facts about what happened:
We have a roof, and what a roof! Beautiful gables, elaborate constructions and a huge attic underneath, which, should we ever get bored, could certainly offer one or two treats for our guests. But for now, let’s concentrate on the planning so far.
The drywall work in the rooms has begun and yes, the rooms have been commissioned. Two weeks ago, we were able to take a close look at a sample room ourselves and are simply thrilled.We have tried to coordinate everything perfectly for you down to the smallest detail.The raw installations for the bathrooms have also been installed.To take this step, kilometers of pipes and cables had to be laid.And in all possible dimensions.Crazy, we tell you.
Thanks to you, we were also able to install the entire air conditioning system, including all the pipes. (Not that we need it in these autumn temperatures, but it’s there 😊 )
The first pictures of the wellness area have also arrived, as you can see at the beginning, and both the tiles and the furnishings have been selected. We have also ordered our future cosmetics line and are looking forward to offering you very special wellness experiences with high-quality products from Janssen Kosmetik from October. And hey, at least the wind can no longer blow through the building, as all the windows and almost all the exterior doors have now been installed. The huge window fronts in the wellness area make quite an impression.
There will be a 270° fireplace in the lounge area of the wellness landscape, which has also been selected and ordered. The electrics in the walls were completed this week and a large plastering team has arrived and is now completing its work.
The first shower sizes can already be seen in the wellness area and cabin sizes can already be guessed.The entire swimming pool technology has also arrived and been installed.
We have also decided to expand our sports and fitness offering even further.In addition to our great yoga offers, the company PTraining from Bomlitz will be moving in with us from October and will be available to you with various courses and a physiotherapist.
When I read through all this again, I’m amazed at the progress that has been made in the last few weeks and I’m sure we’ve already forgotten half of it.
We promise to do better and will now report back at shorter intervals with new events.
Best regards
Your Fuhrhops and team